Turns finalized requirements and design documents into an executable, sequenced build plan. Reads the SRS, use cases, architecture document, and UX-foundations document, then decomposes the system into epics and vertical feature slices — each tracing the FR IDs it implements, the UC IDs it realizes, and the SCR screen IDs it touches — defines the walking skeleton, orders the work by dependency and risk, verifies Must-requirement coverage, specifies the first vertical slice, and lists the engineering foundations to stand up. Use in the planning phase — after software-architecture and ux-foundations, before scaffolding or coding — whenever a designed application needs to become a backlog and a build order. Trigger on "plan the implementation", "break this into epics and features", "what do we build first", "create the build plan", "turn the architecture into a roadmap", or "sequence the work". It stops at the plan; per-slice detailed design and ui design are separate downstream steps.

zeeshanhanif · 已有静态检查记录

安装与使用

运行命令前先阅读来源与依赖说明。复制命令不会自动安装或执行。

npx skills add zeeshanhanif/agentic-sdlc-kit --skill implementation-planning

技能说明


name: implementation-planning description: >- Turns finalized requirements and design documents into an executable, sequenced build plan. Reads the SRS, use cases, architecture document, and UX-foundations document, then decomposes the system into epics and vertical feature slices — each tracing the FR IDs it implements, the UC IDs it realizes, and the SCR screen IDs it touches — defines the walking skeleton, orders the work by dependency and risk, verifies Must-requirement coverage, specifies the first vertical slice, and lists the engineering foundations to stand up. Use in the planning phase — after software-architecture and ux-foundations, before scaffolding or coding — whenever a designed application needs to become a backlog and a build order. Trigger on "plan the implementation", "break this into epics and features", "what do we build first", "create the build plan", "turn the architecture into a roadmap", or "sequence the work". It stops at the plan; per-slice detailed design and ui design are separate downstream steps.

Implementation Planning

This skill is the bridge between design and construction. It takes the requirements and design-phase documents and produces a plan a team (or an agent) can execute: what to build, broken into thin vertical slices, in what order, starting where.

Two principles govern it:

  1. Slice vertically, never horizontally. A unit of work is a thin slice that cuts through every layer — UI, API, domain, data — and delivers something demonstrable. "Build all the tables" or "build all the screens" are horizontal slices: they deliver no value and integrate late. Every feature here spans backend and UI together.
  2. Make the architecture executable before making it complete. The first thing built is the walking skeleton — the minimal end-to-end path that proves the system runs and deploys — not the easiest feature. Sequence the rest by dependency and risk, de-risking the most uncertain decisions early.

It plans the whole application's breadth but only details what's next. Producing implementation-ready detail for the entire backlog upfront is the waterfall trap; this skill gives full breadth and depth-on-demand.

Inputs

Four upstream documents, each read from its default path unless the user provides another. Each degrades independently — a missing document reduces fidelity, it doesn't block (though the plan is materially weaker without the architecture and ux-foundations, which carry the building blocks and screens that make slices vertical).

  • SRS — docs/srs.md. The source of what a feature is: functional requirements with IDs and priorities (MoSCoW feeds sequencing and the coverage check), plus constraints (team, timeline). Skip tombstoned requirements (status Removed/Deprecated) — they must not spawn slices.
  • Use cases — docs/use-cases.md. Slices often realize use cases; their flows are prime slice candidates.
  • Architecture — docs/architecture.md. Building blocks and their dependencies, risky ADRs, runtime scenarios, deployment view, cross-cutting concepts.
  • UX foundations — docs/ux-foundations.md. Surfaces, per-surface screen inventories with SCR IDs, key user flows. (Skip tombstoned screens.)

Source-gated traceability (the pipeline rule): cite an ID — FR/NFR, UC, SCR — only when the document defining it is present; otherwise describe in prose. Never fabricate an ID.

Workflow

Phase 1 — Ingest and frame

Read all four documents (per Inputs). Build a combined picture: the functional requirements by area and priority, the building blocks and their dependencies, the ADRs flagged risky, the surfaces with their screen inventories, and the key user flows. Note constraints (team size, timeline, priorities) so the plan is realistic. Tell the user which documents were found and which are missing.

Phase 2 — Confirm priorities (brief)

Most of what you need is in the documents. Ask only what changes the plan and isn't already answered: what "first" should optimize for (de-risk the scariest part, reach a demoable milestone, or unblock the most downstream work), any fixed deadlines or an MVP cut line, and team capacity if the SRS/architecture didn't say. Keep it short; infer and offer defaults.

Phase 3 — Decompose

Read references/slicing-guide.md. Break the system into epics (aligned to the architecture's building blocks / bounded contexts) and features (thin vertical slices within each epic; "feature" and "slice" are synonyms in this pipeline). Mint a stable ID for every feature: FEAT-NNN, sequential in definition order (not build order — build order can change; IDs never do). Same immutability rules as FR/SCR IDs: never renumbered or recycled; amendments take the next free number; removed features are tombstoned, not deleted. The epic association lives in the table, not the ID — features may migrate between epics without renumbering. For every feature, record its traced touchpoints:

  • FRs implemented (by ID, e.g., FR-AUTH-001..003)
  • UCs realized (by ID, e.g., UC-004)
  • Screens touched (by SCR ID and surface, e.g., SCR-WEB-004, SCR-ADM-002)
  • Building blocks / endpoints (from the architecture)
  • Data (entities read/written)

This is whole-app breadth — every feature, coarse where far off.

Then run the coverage check (see references/slicing-guide.md, Coverage): every non-tombstoned Must-priority FR, and every inventory screen, must be covered by a slice, placed in the foundations, or explicitly excluded. Apply the escalation ladder: self-resolve → ask the user (batched, with your best guess per item) → record unresolved items as explicit open gaps in Risks. Should/Could gaps go straight to the report.

Phase 4 — Define the walking skeleton

Read references/sequencing-guide.md. Specify the walking skeleton: the minimal end-to-end path through the major cont